Move to our new plant 2

On December the 27th we were ready for moving to the new plant.
We have transported 32 machinery on the road to the new production hall “A” and arranged them directly.
To minimize the risk for road traffic, our trainees warned with safety vests and warning flags.
Some measuring machines and masters offices have already moved.
With the support of some employees was up to 05.01.2013 with the help of tractors / trucks / lift trucks, etc. all find their place in Plant 2.
All other departments, such as shipping, installation, clean room, etc. in 2013 accommodated gradually in Plant 2.
We appreciated the smooth running and are all volunteers for your support greatly appreciated.